Cheyenne Light files Microsoft data center grid agreements at FERC

The utility says Microsoft is paying for the build-out of three Wyoming data centers, and it filed the redacted agreements with FERC while disputing that the commission has jurisdiction over them.

Cheyenne Light, Fuel and Power Co. said in a Nov. 24, 2026 filing at the Federal Energy Regulatory Commission that it has agreements to build distribution and transmission infrastructure for three planned Microsoft data centers in Wyoming. The agreements are redacted.

Microsoft pays for the infrastructure through contribution-in-aid-of-construction payments, Utility Dive reported. Cheyenne Light told FERC it does not believe the commission has jurisdiction over these retail agreements. It filed them out of an abundance of caution, it said, because of FERC's recent statements on cost recovery for transmission built for large loads.

The utility plans to serve the data centers under its Large Power Contract Service tariff and a proposed Large Customer Transmission Cost Adjustment Mechanism. Both are designed to insulate its other customers from infrastructure costs. Cheyenne Light plans to use the transmission tariff to recover the costs of two proposed transmission projects totaling $686 million. Those projects are needed to serve large loads, including a Google data center.

Cheyenne Light is a subsidiary of Bright Horizon Energy Corp., which was formed by the Nov. 13 merger of Black Hills Corp. and NorthWestern Energy Group. Black Hills officials said the utility is executing on a 3 GW data center pipeline, including 600 MW of Microsoft and Meta projects, with another 2.5 GW in early-stage talks.

The scale is large against the existing system. Cheyenne Light serves about 46,000 retail customers and set a peak load record of 439 MW in July 2026. The 600 MW of Microsoft and Meta projects alone exceeds that peak.