# Columbia council takes up stalled south Columbia transmission line
- URL: https://www.gridlinedaily.com/columbia-council-takes-up-stalled-south-columbia-transmission-line/
- Published: 2026-11-15T01:54:44.000Z
- Updated: 2026-11-15T01:54:44.000Z
- Description: The City Council will take public comment Monday, Nov. 16, on a revived 161-kilovolt line in Ward 5, a project first proposed 11 years ago and paused after homeowner opposition.
- Author: Gridline Staff
- Tags: Grid, #auto

The full Columbia City Council will hear from residents Monday, Nov. 16, about a revived high-voltage transmission project in Ward 5, according to the Columbia Daily Tribune (via Yahoo). The project was first proposed 11 years ago and is back before the council after opposition and further study.

The proposed route would start at the Perche Creek Substation and run south on Scott Boulevard to Vawter School Road. From there it would head east along Nifong Boulevard and Grindstone Parkway to the Grindstone Substation. A substation is a facility where voltage is stepped up or down and power is routed onward to customers. The city says the line would be 161-kilovolt, a voltage class used to move large amounts of power between substations, and says it was originally approved in 2015.

The Tribune reports that the main concern remains electric and magnetic fields, which are the fields produced around energized power lines, with the route running near a school.

Money and history shape the debate. Columbia voters approved a $63 million bond issue for the project in 2015, according to KOMU. The council paused the project in 2016 after homeowners along the path complained. At a February 2026 meeting, the City of Columbia says, the council directed Utilities to move forward with the Vawter School Road route.

ABC17 reported that the city's utility advisory board called the project's $34 million price tag steep but necessary given the city's growth.

The reliability argument centers on the Perche Creek substation. KOMU reported that it relies on a single 161-kilovolt line, which creates vulnerability during peak demand, when customers use the most electricity. A second line would give the substation another path for power. Monday's hearing gives residents a chance to weigh in on that tradeoff before the project advances.

---

**Sources:** [Columbia Daily Tribune (via Yahoo)](https://www.yahoo.com/news/us/articles/council-decision-stalled-electric-transmission-190101380.html?ref=gridlinedaily.com), [City of Columbia](https://www.como.gov/city-source/april-2026/city-major-electric-projects/?ref=gridlinedaily.com), [KOMU](https://www.komu.com/news/midmissourinews/columbia-city-council-considers-two-routes-for-electric-transmission-line-again/article%5F6150cae6-0038-4541-ae9e-bf32ea5bfade.html?ref=gridlinedaily.com), [ABC17 News](https://abc17news.com/news/top-stories/2026/02/11/columbia-utility-board-recommends-vawter-school-road-route-for-new-electric-transmission-line/?ref=gridlinedaily.com)

*This story was produced by Gridline's automated desk from the reporting linked above.*